So progress has seemed slow although we continue to get work done. Inspections on the new power panel are complete (and approved). Still waiting for Xcel Energy to come and switch our main power from one panel to to other. This will be a fun day because we lose all our heat and lighting until I rewire the old panel (good to have a generator and a wood stove). Now have the stairs installed so can access the house through the garage. Work now is aimed at getting the rough electrical, plumbing and mechanical complete so we can get the next round of inspections completed (then we can start to do some insulation). Windows should show up on the 18th. Garage doors should be about the same time. Pictures are of stairs, utility room in garage, and the new table saw.
Thursday, December 13, 2007
Wednesday, November 21, 2007
Saturday, November 10, 2007
Good progress, and none to soon. 50% chance of snow for Monday. Roof is not completely sheathed but better than nothing. The framer hoped to be done today but just taking longer than estimated (nothing new). Pictures of tubing are the radiant floor heat we are retrofitting into the existing house (in the crawlspace).
Saturday, November 3, 2007
Great weather has allowed good progress on the framing. A 3 man crew has been working for 8 days now and is about 60% complete. Weather looks good for another week so hope to have the roof on and covered.Timber framer is complete except for some sanding and touch up work. Probably won't get the windows in till mid December.
Sunday, October 28, 2007
Saturday, October 20, 2007
Thursday, October 18, 2007
Wednesday, October 10, 2007
Monday, September 24, 2007
I've been a bit delinquent at updating the blog. Progress is being made but is not that visible. The excavator is finally complete backfilling the foundation. We had to bring in 7 trucks of fill (after hauling out over 30 since we had no place to store). The timber framer is about 50% complete preparing the timber frame. He is hoping to raise it around October 15th. We did get the power lines, well power, comcast, quest, and the propane lines buried as well. Propane tank will be delivered on Wednesday. The material for the radiant heating system will begin showing up so we can retrofit the existing house. Overall have had great weather. Did get about 2" of snow one day but was gone the next. We are also trying to contract to get the roof and remaining walls framed so that we are closed in before any big snows.
Sunday, September 2, 2007
Sunday, August 26, 2007
Monday, August 13, 2007
Tuesday, July 24, 2007
Wednesday, June 27, 2007
More water and mud slide problems are causing a delay. We are not comfortable with the safety of the situation so we are going to take a step back and move our addition 6 ft to the west. This will make the excavation easy from here out and will also improve the long term drainage issues. Of course every change costs $. Hot tub is looking iffy.
Sunday, June 24, 2007
We have been struggling with the excavation part of the project. We have run into quite a bit of water seepage which has been causing the dirt to sluff off into our work area. Lots of mud as well. I think we have cut the bank back far enough now and added a plywood barrier for the dirt to fall against. Also had to cut our real big tree down, something we did not want to do. Fortunately it fell the direction we wanted it to.
Friday, June 8, 2007
Lots of progress with week with my dad and brother up here. They actually came to ride their ATVs around but also used them to move wood around. Got the two big trees cut up and hauled off. Also got the deck removed and taken to the dump. Silt fence is complete and inspected by the engineering department (thanks Jeff for the last 30 ft of trench). Lastly installed the temporary support under the house so it does not fall down during excavation. So, we are basically ready for the excavator.
Saturday, May 19, 2007
Bought a trailer to haul material, equipment, and stuff to the dump. Got a good deal on a 10,400# PJ Trailer in Parker, Co.
Also found a new way into the crawl space from the outside. It had been covered over with insulation. This will eliminate the need to go through the house for the work that must be done down there.
Subscribe to:
Posts (Atom)