Sunday, February 13, 2011

Moved Kitchen







We took a big step and moved the old kitchen into the new addition temporarily until we build cabinets and buy some appliances. Worked out pretty well. The sink area was in the same configuration as the new one so fit well. The old peninsula became the new island. Everything else just found a place. By making this move, we can complete the electrical and plumbing in the old part of the house so we can get our last rough inspections. Once that is complete, we can start finishing the entire house. Thanks to Tim Cole for coming up for the weekend to help us.

Sunday, February 6, 2011

Railing on Loft


Now have the center portion of the loft railing complete. Hope to have the rest the drywall up in the addition this week and then possibly move the kitchen next weekend.

Tuesday, January 11, 2011

Finished High Up Drywall and Staining




This week we finished using the scaffolding to put the sealer on the timber frame and put up the drywall in the high areas. Also installed a fan the the electrical for the two lights that are way up there.


Tuesday, January 4, 2011

Putting on the wood sealer

Last few days have not been very eventful but have been productive. Now have the clear wood preservative on 80% of the high ceiling and timber frame. Only have the scaffolding one more week so focusing on everything high.

Thursday, December 30, 2010

First Update (and last) for 2010





We'll, finally getting to spend some serious time working on the addition. Although we have made some progress over time, just now feeling like we might getthis done.





On the exterior, we have completed the roof on the addition and the channel siding (still have some rock and shingle siding to do).

Inside we are working on the ceiling and walls. Have most the high ceiling in and starting to apply the clear wood preservative.












The Radiant floor heating system is in and working for the entire house. So far has been working great.











The new laundary room, pantry, and master bedroom rooms are framed in. Hard to show a picture since just looks like a bunch of studs. Do have a picture of the rough plumbing for the laundary room.

Sunday, March 16, 2008

Made some good progress while Uncle Moe was in town. Completed the loft floor and wall, built the aluminum pans for the window installation and installed a water resistent wall in the utility room. Thanks alot Moe.

Since then, have mostly just been watching the snow build up. See photos. Really don't need a ladder anymore to get onto the roof.

Tuesday, February 12, 2008



Has been a while since last update for good reason. Really have not done that much. Working on plumbing, electrical and some interior items. Thanks to Louise (Renee's mom) for helping out with loft floor installation and pulling wire for the kitchen electrical. We also got all the soffit cedar material stained during one warm day (the only day that has been over 40 deg since November). Will start to install that as weather get s better (at least around freezing).